Another windfarm on the way for West Clare?

This article is from page 12 of the 2011-05-31 edition of The Clare People. OCR mistakes are to be expected so download the original SWF or the rendered page 12 JPG

WEST CLARE could be about to get another wind energy project worth millions of euro in the development stage as a new application to construct a windfarm at Shanovogh near Miltown Malbay has been lodged with Clare County Council planners.

McMahon Finn Wind Acquisitions Ltd are planning to build the windfarm on a site that’s two miles away from West Clare Renewable Energy project on Mount Callan, the green light for which was given by Clare County Council last August.

The application lodged with Clare County Council last Friday is for a windfarm comprising of six turbines with a height of 85 metres and was submitted to local authority planners by Cian Ó Laoithe Architects.

Last year, Clare County Council invalidated plans submitted by McMahon Wind Ltd for a 12-turbine wind farm on the same site, while a decision date on the new planning application is due in mid-July.

The latest application for a windfarm development in the county falls within the guidelines of the Clare County Council wind energy strategy that has set a working target of 550 MW of wind energy to harnessed in the county by 2020.

Between 2000 and 2010, 22 applications for wind farms were lodged with Clare County Council, with one of the first projects to be given the green light being in 2002 when the ESB were granted permission for a nine-turbine € 20 million renewable energy farm at Moneypoint.

Most recently, last December An Bord Pleanala has rejected an appeal by An Taisce against a Clare County Council decision to allow Hibernian Windpower to construct a wind farm incorporating 11 turbines of approximately 2500kW capacity each, at Boolynageragh, Lissycasey.

The development site, which is three kilometres north of Lissycasey, will have a total rated electrical output of 27.5MW. The capital cost of the project is up to € 50m, while the Mount Callan windfarm that’s set to be the largest community-owned windfarm development in Ireland is a € 200m project that aims to create 300 jobs during the construction phase.

It has been claimed that renewable energy area in Clare has the capacity to create 10,000 jobs in the county from now until 2020.